Jal Jeevan Mission – Water Supply Infrastructure
Piped water supply for 18 villages: pipelines, household water connections and RCC overhead tanks.
Key quantities
About this project
Water supply works under the Jal Jeevan Mission across 18 villages in the Mohla-Manpur, Kanker and Rajnandgaon divisions: about 8,000 km of pipeline, 5,000 household water connections and RCC overhead tanks in 10 villages.
Request a QuoteWater supply infrastructure under the Jal Jeevan Mission, Government of Chhattisgarh, bringing piped water to households in 18 villages across the Mohla-Manpur, Kanker and Rajnandgaon divisions. The project was completed in 2026.
Scope of work
- Pipeline laying, about 8,000 km in total
- Water connections to 5,000 households
- RCC overhead water tanks of 40 KL, 60 KL and 120 KL capacity in 10 villages
- Coverage: 18 villages in the Mohla-Manpur, Kanker and Rajnandgaon divisions
- Community meetings with village representatives during execution
Other projects
Completed
SAIL – Bhilai Steel Plant Bhilai Warehouse Development
Warehouse development works inside Bhilai Steel Plant: structural fabrication and erection, large-area bituminous works, RCC drains, high-ma...
Completed
CSIDC Engineering Park Development, Bhilai
Infrastructure works for the CSIDC Engineering Park in Bhilai: bituminous roads, drains, site development, divider painting, street lighting...
Completed
Public Works Department (PWD) Rana Khuji to Renga Dabri Road
A rural road for the Public Works Department: about 8 km of bituminous road built up from subgrade, with 10 km of RCC drains, 20 pipe culver...
Completed
SAIL – Bhilai Steel Plant (Medical Department) Strengthening & Re-plastering of Ward Blocks, JLNH&RC Bhilai
Strengthening and re-plastering of the old ward blocks, isolation ward, OPD block and other units at JLNH&RC Bhilai for the Medical Departme...
Completed
SAIL – Bhilai Steel Plant Repair of Differential Settlement, Flyover-2 over CEZ Circle
Execution of work for repair of the differential settlement observed in Flyover-2 over CEZ Circle, Bhilai, Distt-Durg, from May 2024 to Apri...
Completed
SAIL – Bhilai Steel Plant Flyover No. 2 – Balance Civil Works (PKG No. 111-01C)
Balance of civil works for construction of Flyover No. 2 at Bhilai Steel Plant (PKG No. 111-01C), Bhilai, Distt-Durg, from May 2021 to March...