Relocation of CMO Warehouse, Disposal Stores and Other Facilities
Enabling works for the Universal Rail and Structural Mill: 55 acres developed with bitumen hardstand, roads, drains, railway track, buildings and CCTV.
Key quantities
About this project
Relocation of the CMO warehouse, disposal stores and other facilities at Bhilai Steel Plant under Enabling Works Package No. 0 for the Universal Rail and Structural Mill: 55 acres developed with a bitumen hardstand, 8 km of roads, 13 km of drains, 6 km of railway track and 60 CCTV cameras.
Request a QuoteRelocation of the CMO warehouse, disposal stores and other facilities under Enabling Works Package No. 0 for the installation of the Universal Rail and Structural Mill at SAIL – Bhilai Steel Plant.
Scope of work
- Area developed – 55 acres, with a bitumen hardstand for heavy-duty operations
- Roads – 8 km
- Drains – 13 km
- Railway track – 6 km
- Concrete buildings – 50,000 m³
- Material handling – 3,000 MT
- Electrical work – 33 high-mast lights and a 33 kV substation
- CCTV surveillance – 60 cameras
The photographs include the bhoomi pujan at the start of work, a project board meeting and construction progress on site.
Other projects
Completed
SAIL – Bhilai Steel Plant Bhilai Warehouse Development
Warehouse development works inside Bhilai Steel Plant: structural fabrication and erection, large-area bituminous works, RCC drains, high-ma...
Completed
CSIDC Engineering Park Development, Bhilai
Infrastructure works for the CSIDC Engineering Park in Bhilai: bituminous roads, drains, site development, divider painting, street lighting...
Completed
Public Works Department (PWD) Rana Khuji to Renga Dabri Road
A rural road for the Public Works Department: about 8 km of bituminous road built up from subgrade, with 10 km of RCC drains, 20 pipe culver...
Completed
SAIL – Bhilai Steel Plant (Medical Department) Strengthening & Re-plastering of Ward Blocks, JLNH&RC Bhilai
Strengthening and re-plastering of the old ward blocks, isolation ward, OPD block and other units at JLNH&RC Bhilai for the Medical Departme...
Completed
Jal Jeevan Mission, Govt. of Chhattisgarh Jal Jeevan Mission – Water Supply Infrastructure
Water supply works under the Jal Jeevan Mission across 18 villages in the Mohla-Manpur, Kanker and Rajnandgaon divisions: about 8,000 km of...
Completed
SAIL – Bhilai Steel Plant Repair of Differential Settlement, Flyover-2 over CEZ Circle
Execution of work for repair of the differential settlement observed in Flyover-2 over CEZ Circle, Bhilai, Distt-Durg, from May 2024 to Apri...